The roof took over 3 weeks to finish. Some of the pieces were ordered wrong and had to be reordered. We have had a lot of rain as well, and a steep metal roof becomes a dangerous slide when wet. Anyway, it is on now.
Last Friday (11/30), the addition was insulated. This is great! It is still drafty in the house, but it it is a whole lot better than it was.

Upstairs.

Master bathroom windows.
Monday (12/3) saw no progress. On Tuesday (12/4), the electrician came to do a few small additions and some minor changes. Jim and Ralph did some minor interior details. The most exciting thing to happen was that we broke open the wall where the access to the new addition will be.

Looking back to the dining room from the new hall.
Wednesday (12/5) was spent on the new front entry. The new small square window was added and the porch framing was sheathed. You can really see the form on the front better now.