Thursday, January 17, 2008

Drywall

The drywall process has been a long, slow one.  The gypsum board was put up by one crew a couple weeks before Christmas.  That was nailing and screwing the boards and adding metal to all the corners.

The next crew came to tape the seems and plaster the seems and nails/screws.  This is a 4 step process that needs a day or two to dry between each step.  The holidays greatly lengthened this process!

The last 2 steps required another crew.  This crew put primer on all the walls one day and came back a few days later to spray on the texture.  Well, that got done yesterday, and it is still drying today.

Now we can paint!





















Upstairs.
















Door to balcony upstairs.















Ceiling in Master Bedroom.